Heating or cooling the entire large space requires substantial air conditioning installation and operating costs.
The packing zone, where packing and sorting are concentrated, heats up more quickly in summer. The existing system could not precisely cool only the occupied area.
Air conditioners alone could not deliver cool air far enough or distribute it uniformly throughout the work zone.
Fabric ducts were arranged in a straight line above the packing line, concentrating cooling on the work area rather than dispersing it into unused space.
A dedicated plenum and fabric ducts connected to the top of the existing air conditioner, creating a spot-cooling system for the main work zone without replacing equipment.
Instead of increasing air conditioning capacity, we optimized air distribution to deliver cool air effectively to the locations that needed it, reducing costs.
Even in midsummer, the fabric duct work zone maintained a comfortable temperature of approximately 26°C, delivering cooling workers could immediately feel.
Rather than cooling the entire 300-pyeong facility, the system focused on occupied areas and was implemented for approximately KRW 3 million.
The modular zip-connected structure makes it relatively easy to reposition or extend the ducts when the production line changes.